Question: Problem 13-2 (Static) The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item Lead time (wk)
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Click here for the ExcelData Fle a. If 20 units of the end item are to be assembled, how many additional units of E are needed? (Hint You don't need to develop an MRP plan to determine this.)