Question: Problem 13-21 Consider the following project network and activity times (in days): The crashing data for this project are as follows: Identify the critical activities
Problem 13-21
Consider the following project network and activity times (in days):

The crashing data for this project are as follows:
- Identify the critical activities and find the expected project completion time.
Project Completion Time = ______daysActivity Critical A Yes B No C Yes D No E Yes F No G No - What is the total project cost using the normal times? $_____