Question: Problem 9 - 2 2 ( Algorithmic ) Consider the following project network and activity times ( in days ) . Assume that management desires

Problem 9-22(Algorithmic)
Consider the following project network and activity times (in days). Assume that management desires a 12-day project completion time.
\table[[Activity,A,B,C,D,E,F,G],[Time,2,2,5,5,6,2,2]]
The crashing data for this project are as follows:
\table[[,Time (days),Cost ($)],[Activity,Normal,Crash,Normal,Crash],[A,2,1,700,1100],[B,2,1,1300,1500],[C,5,3,2300,3300],[D,5,3,1400,2000],[E,6,4,1800,3200],[F,2,1,700,1000],[G,2,1,600,1000]]