Question: PROBLEM 14 A precedence diagram is shown. Which activity has the greatest free float? B D 3 5 8 8 3 15 F-F = 2

PROBLEM 14 A precedence diagram is shown. Which

PROBLEM 14 A precedence diagram is shown. Which activity has the greatest free float? B D 3 5 8 8 3 15 F-F = 2 11 6 17 8 5 13 A 0 30 3 0 3 E 9 6 13 15) 4 19 H 19 3 19 22 0 22 3 63 909 F 9 7 9 16 0 16 G 17 2 17 190 19 F-S = 1 key ES = earliest start EF = earliest finish D = duration LS - latest start LF - latest finish TF = total float F-F = finish to start F-S = start to start activity description ES DLS EF TE LF (A) activity B (B) activity D (C) activity E (D) activity F Hint: Free float is calculated by subtracting the earliest finish of an activity from the earliest start of its successor activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock