Question: Problem 14-1 (Algo) Using the BOM shown below, A 2 weeks B (1) 1 week C (2) 2 weeks D (3) 3 weeks E (2)

Problem 14-1 (Algo) Using the BOM shown below, A

Problem 14-1 (Algo) Using the BOM shown below, A 2 weeks B (1) 1 week C (2) 2 weeks D (3) 3 weeks E (2) 3.7 weeks F(1) 5.7 weeks C(1) 2 weeks E (4) 3.7 weeks a. How many of part E will be needed if 21 units of end item A are needed? Number of parts needed E b. How many part Cs will be needed? Number of parts needed