Question: Problem 14-2 (Algo) Using the BOM shown below, 3 weeks B (4) 2 weeks C (3) D (1) 3 weeks 2 weeks F (2) E

Problem 14-2 (Algo) Using the BOM shown below, 3

Problem 14-2 (Algo) Using the BOM shown below, 3 weeks B (4) 2 weeks C (3) D (1) 3 weeks 2 weeks F (2) E (4) 5.2 weeks C (2) 2 weeks E (2) 5.2 weeks 6.2 weeks What is the cumulative lead time for end item A? (Round your answer to 1 decimal place.) Cumulative lead time weeks