Question: Problem 15-3 (Static) Answer these questions for the following simple set of project tasks. Task times are shown in hours. A 2 D 5 C

Problem 15-3 (Static) Answer these questions for
Problem 15-3 (Static) Answer these questions for
Problem 15-3 (Static) Answer these questions for the following simple set of project tasks. Task times are shown in hours. A 2 D 5 C 2 B 4 E 6 a. What is the expected time that all five tasks will be completed? Expected time hours Suveo a. What is the expected time that all five tasks will be completed? Expected time hours 03:22-47 b. What is the earliest start for task C? Earliest start thind hour erences c. What is the latest start for task A? Latest start thind hour