Question: Problem 15-4 Answer these questions for the following simple set of project tasks. Task times are shown in hours. B 3 3 a. What is

Problem 15-4 Answer these questions for the

Problem 15-4 Answer these questions for the following simple set of project tasks. Task times are shown in hours. B 3 3 a. What is the length of the critical path? Length of the critical path 22 hours b. What are the earliest start and latest start for E? Earliest thd hour X thd start Latest start 11 hour c. What is the latest start for B? * thd hour Latest 13 start