Question: Problem 15-4 Answer these questions for the following simple set of project tasks. Task times are shown in hours. WI a. What is the length

Problem 15-4 Answer these questions for the

Problem 15-4 Answer these questions for the following simple set of project tasks. Task times are shown in hours. WI a. What is the length of the critical path? Length of the critical path hours b. What are the earliest start and latest start for E? Earliest start thd hour thd hour Latest start c. What is the latest start for B? Latest start thd hour d. If all other tasks are completed in their expected durations, will the project length be affected if task B actually takes four hours instead of the expected two? Yes No