Question: Problem 16-12 (Static) A shoe repair operation uses a two-step sequence that all jobs in a certain category follow. A 27 45 Workstation A Workstation

Problem 16-12 (Static) A shoe repair operation

Problem 16-12 (Static) A shoe repair operation uses a two-step sequence that all jobs in a certain category follow. A 27 45 Workstation A Workstation B JOB TIMES (minutes) B C D E 18 70 26 33 10 15 woo 30 24 Click here for the Excel Data File a. Find the sequence that will minimize total completion time. The sequence is B-A-C-D-E b. Determine the amount of idle time for workstation B. Idle time minutes