Question: Problem 2 ( 1 0 Points, 2 . 5 points each, - 1 . 2 5 per error ) You have a set of 1

Problem 2(10 Points, 2.5 points each, -1.25 per error)
You have a set of 15 potential projects from which you must select a subset of projects. We will use binary variables X1... X15, where if a project is selected, then its corresponding variable =1,0 otherwise. Formulate each of the four constraints below and ensure that you show your work and list your variables in the correct order. Note: You do not need to define the variables or the objective function for this problem.
Constraint 1) Project 14 could be selected if and only if all of Project 1, Project 2, & Project 9 are selected.
Constraint 2) Project 15 must be selected if Project 5 is selected. Project 5 must be selected if Project 15 is selected.
Constraint 3) Project 13 must be selected if Project 8 is selected. The reverse is not true.
Constraint 4) Project 11 must be selected if all of Projects 1,2,3,4,5,6, & 7 are selected.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!