Question: Problem 2 ( 1 0 points ) You have been assigned to lead a new project that requires programmers. The current plan assumes that you
Problem points
You have been assigned to lead a new project that requires programmers. The current plan
assumes that you have all the programmers available, but your manager has just called to say that
another project requires some of the programmers and you'll have to make do with only two.
Develop a resource schedule to determine a new completion date for your project, assuming only
two programmers are available. Use the heuristics described in the text: minimum slack,
smallest duration, and lowest WBS identification number. No splitting of activities is
possible.
MGMT Project Management
a What is the duration of the project, before assigning resources programmers
b Complete the resource schedule below, showing the allocation of the two
programmers that are available for this project. What is your final duration for the
project after allocating the two programmers?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock