Question: Problem 2 ( 1 2 points ) Schedule the precedence diagram for the following project. Determine the ES / EF and L S L F

Problem 2(12 points)
Schedule the precedence diagram for the following project. Determine the ES/EF and LSLF,FFTF and identify the CP.
This problem is to be solved by hand. You may sue Visio or Word or BlueBeam. DO NOT use a scheduling software.
\table[[Activity Description,Duration (days),Predecessors],[1. Mobilize,1,],[2. Clearing and Grubbing,3,1],[3. Lay out fence alignment,1,2],[4. Deliver posts to site,3,3SS/1],[5. Auger post holes,7,4SS/2],[6. Set post in holes,7,5SS],[7. Backfill and plum posts,10,6SS/1],[8. Install boards on fence,5,7 FF],[9. Paint board fence,12,8SS/2],[10. Plant shrubs along fence,\table[[7,0]],8SS/8],[11. Final inspection,1,8,9FS/2,10],[12. Demobilize,1,11]]
Problem 2 ( 1 2 points ) Schedule the precedence

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!