Question: Problem 2 (20 points) For the given project data determine the following: (a) Normal completion time and cost. (b) Crash the project as far as

Problem 2 (20 points) For the given project data

Problem 2 (20 points) For the given project data determine the following: (a) Normal completion time and cost. (b) Crash the project as far as possible and calculate the most economical crash cost and time. Immediate Expected time Normal Bxpediting cont Minimum time Activity predeoston (works) cout($) per wook (s/weak) (weeks) 3 3,000 1,500 2 B 6 7,200 1,000 A 2 2,000 2.000 1 D 7 7,000 2,000 3 CB 1 4.000 1 F B 3 3,000 1,500 2 Answer the following questions