Question: Question 29 (4 points) For the given project data determine the following: a. Normal completion time and cost. b. Crash the project as far as

Question 29 (4 points) For the given project data determine the following: a. Normal completion time and cost. b. Crash the project as far as possible and calculate the most economical crash cost and time. Espected time (weela) Normal cout() Bepad get pad (int) CAVAA 3,000 7200 2,000 7.000 4.000 3.000 1.000 2mo 2000 1 1 3 1 22 1,500 Question 29 (4 points) For the given project data determine the following: a. Normal completion time and cost. b. Crash the project as far as possible and calculate the most economical crash cost and time. Espected time (weela) Normal cout() Bepad get pad (int) CAVAA 3,000 7200 2,000 7.000 4.000 3.000 1.000 2mo 2000 1 1 3 1 22 1,500
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
