Question: Problem 2 : ( 3 5 ) Problem 2 : ( 3 5 ) Given: A project status report was submitted to your office after
Problem : Problem :
Given: A project status report was submitted to your office after weeks of
construction. Budget and Actual Costs and quantities of work in progress are
shown in the figure below.
EARNED VALUE ANALYSIS
PROJECT STATUS REPORT EarthWorks, Inc.
Find: Show all calculations
Project Percent Complete
Project Cost Variance CV and Performance Index CPI
a OverOnUnder Budget?
Project Schedule Variance SV and Performance Index SPI
a BehindOnAhead of Schedule?
Which activities need corrective action to maintain budget and
schedule?
Given: A project status report was submitted to your office after weeks of
construction. Budget and Actual Costs and quantities of work in progress are
shown in the figure below.
EARNED VALUE ANALYSIS
PROJECT STATUS REPORT EarthWorks, Inc.
Find: Show all calculations
Project Percent Complete
Project Cost Variance CV and Performance Index CPI
a OverOnUnder Budget?
Project Schedule Variance SV and Performance Index SPI
a BehindOnAhead of Schedule?
Which activities need corrective action to maintain budget and
schedule?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock