Question: Problem 2 : ( 3 5 ) Problem 2 : ( 3 5 ) Given: A project status report was submitted to your office after

Problem 2: (35) Problem 2: (35)
Given: A project status report was submitted to your office after 13 weeks of
construction. Budget and Actual Costs and quantities of work in progress are
shown in the figure below.
EARNED VALUE ANALYSIS
PROJECT STATUS REPORT- EarthWorks, Inc.
Find: (Show all calculations)
Project Percent Complete (5)
Project Cost Variance (CV) and Performance Index (CPI)(5)
a. Over/On/Under Budget? (5)
Project Schedule Variance (SV) and Performance Index (SPI)(5)
a. Behind/On/Ahead of Schedule? (5)
Which activities need corrective action to maintain budget and
schedule? (10)
Given: A project status report was submitted to your office after 13 weeks of
construction. Budget and Actual Costs and quantities of work in progress are
shown in the figure below.
EARNED VALUE ANALYSIS
PROJECT STATUS REPORT- EarthWorks, Inc.
Find: (Show all calculations)
Project Percent Complete (5)
Project Cost Variance (CV) and Performance Index (CPI)(5)
a. Over/On/Under Budget? (5)
Project Schedule Variance (SV) and Performance Index (SPI)(5)
a. Behind/On/Ahead of Schedule? (5)
Which activities need corrective action to maintain budget and
schedule? (10)
 Problem 2: (35) Problem 2: (35) Given: A project status report

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!