Question: Problem 2 (5 pts) Use the process Information provided in the following table, when the sequence of flow is B (any machine can be used

 Problem 2 (5 pts) Use the process Information provided in the

Problem 2 (5 pts) Use the process Information provided in the following table, when the sequence of flow is B (any machine can be used if available) C D (any machine can be used if available). Operation Number of Units of Equipment Design Capacity (by equipment) 240 units/hr 130, 120, 160, 110 250 units/hr 140, 95 Planned Utilization (overall) 57.5% 82.0% 77.0% 62.5% Calculate the maximum (design) capacity of the entire process and effective capacity of the entire process