Question: Use the process information provided in the following table, when the sequence of flow is A B (any machine can be used if available) C

Use the process information provided in the following table, when the sequence of flow is A B (any machine can be used if available) C D (any machine can be used if available).
| Operation | Number of Units of Equipment | Design Capacity (by equipment) | Planned Utilization (overall) |
| A | 1 | 300 units/hr | 76.0% |
| B | 4 | 70, 60, 100, 50 | 82.5% |
| C | 1 | 310 units/hr | 67.0% |
| D | 2 | 200, 75 | 85.0% |
Use the process Information provided in the following table, when the sequence of flow Is A - B (any machine can be used if available) -C-D (any machine can be used if available). Operation A B C D Number of Units of Equipment 1 4 1 2 Design Capacity (by equipment) 300 units/hr 70, 60, 180, 50 310 units/hr 200, 75 Planned Utilization (overall) 76.0% 82.5% 67.0% 85.0% Calculate the maximum (design) capacity and effective capacity. (Round "Effective capacity" to 2 decimal places.) Units/hr a. Maximum capacity Effective capacity b
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts