Question: Problem 2 . A plant manager needs a design for an assembly line to assembly a new product that is being introduced. The time requirements

Problem 2. A plant manager needs a design for an assembly line to assembly a new product that is being introduced. The time requirements and immediate predecessors for the work elements are as follows:
\table[[\table[[Work],[Element]],Time (sec),\table[[Immediate],[Predecessor]]],[A,12,-],[B,60,A],[C,36,-],[D,24,-],[E,38,C, D],[F,72,B, E],[G,14,-],[H,72,-],[I,35,G, H],[J,60,I],[K,12,F, J],[Total =,435,]]
If the desired output rate is 30 units per hour, arrange the activities to 4 work stations.