Question: Problem 2 A Project has been defined to contain the following list of activities along with their required times for completion and predecessor(s) Note: Please

Problem 2

A Project has been defined to contain the following list of activities along with their required times for completion and predecessor(s)

Note: Please use problem 2 information and work on problem 3.

Activity Immediate activity Time (weeks) Predecessors
1 Collect requirements 3
2 Analyze processes 2 1
3 Analyze data 2 2
4 design processes 6 2
5 design data 3 3
6 design screens 2 3,4
7 design reports 4 4,5
8 program 5 6,7
9 test and document 7 7
10 install 2 8,9

a) Draw a network diagram

b) Calculate the earliest expected completion time

c) Show the critical path in your network diagram

d) What would happen if activity 6 were revised to take six weeks instead of two weeks?

Note: Please use the above information and work on the below questions.

Problem 3

Using MS Project or Project Libre software, you will complete

1. A Gantt Chart for the project described in the table for problem 2

2. A Gantt Chart and a network diagram that includes the modification indicated on step d.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!