Question: Problem 2 A Project has been defined to contain the following list of activities along with their required times for completion and predecessor(s) Note: Please
Problem 2
A Project has been defined to contain the following list of activities along with their required times for completion and predecessor(s)
Note: Please use problem 2 information and work on problem 3.
| Activity | Immediate activity | Time (weeks) | Predecessors |
|---|---|---|---|
| 1 | Collect requirements | 3 | |
| 2 | Analyze processes | 2 | 1 |
| 3 | Analyze data | 2 | 2 |
| 4 | design processes | 6 | 2 |
| 5 | design data | 3 | 3 |
| 6 | design screens | 2 | 3,4 |
| 7 | design reports | 4 | 4,5 |
| 8 | program | 5 | 6,7 |
| 9 | test and document | 7 | 7 |
| 10 | install | 2 | 8,9 |
a) Draw a network diagram
b) Calculate the earliest expected completion time
c) Show the critical path in your network diagram
d) What would happen if activity 6 were revised to take six weeks instead of two weeks?
Note: Please use the above information and work on the below questions.
Problem 3
Using MS Project or Project Libre software, you will complete
1. A Gantt Chart for the project described in the table for problem 2
2. A Gantt Chart and a network diagram that includes the modification indicated on step d.