Question: 1 . Search the web for four different project management software packages. o What are the relative strengths and weaknesses of each packaged software? o
Search the web for four different project management software packages.
o What are the relative strengths and weaknesses of each packaged software?
o What advice would you give to someone intending to buy project management soft ware for his or her PC Why?
A project has been defined to contain the following list of activities along with their required times for completion.
Activity No Activity Time Weeks Immediate Predecessors
Collect Requirements
Analyze processes
Analyze data
Design processes
Design Data
Design screens
Design Reports
Program
Test and document
Install
a Show the Gantt Chart for the activities.
b Calculate the earliest expected completion time of the project in weeks
c What would happen if activity were revised to take six weeks instead of one week be specific
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock