Question: 1 . Search the web for four different project management software packages. o What are the relative strengths and weaknesses of each packaged software? o

1. Search the web for four different project management software packages.
o What are the relative strengths and weaknesses of each packaged software?
o What advice would you give to someone intending to buy project management soft ware for his or her PC? Why?
2. A project has been defined to contain the following list of activities along with their required times for completion.
Activity No. Activity Time (Weeks) Immediate Predecessors
1 Collect Requirements 2--
2 Analyze processes 31
3 Analyze data 32
4 Design processes 72
5 Design Data 62
6 Design screens 13,4
7 Design Reports 54,5
8 Program 46,7
9 Test and document 87
10 Install 28,9
a. Show the Gantt Chart for the activities.
b. Calculate the earliest expected completion time of the project (in weeks).
c. What would happen if activity 6 were revised to take six weeks instead of one week (be specific)?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!