Question: Problem 2 Chapter 10: Currently a company that designs Web sites has five customers in its backlog. The time since the order arrived, processing time,
Problem 2
Chapter 10: Currently a company that designs Web sites has five customers in its backlog. The time since the order arrived, processing time, and promised due dates are given in the following table.
| Job | Time Since Order Arrived (days ago) | Processing Time (days) | Due Date (days from now) |
| A | 6 | 18 | 66 |
| B | 3 | 24 | 58 |
| C | 2 | 32 | 80 |
| D | 10 | 22 | 26 |
| E | 8 | 12 | 50 |
- Create a schedule using the first-come first-serve (FCFS) rule, calculating the average flow time and average days past due.
- Create a schedule using the earliest due date (EDD) rule, calculating the average flow time and average days past due.
- Comment on the performance of the FCFS and EDD rules relative to average flow time and average days past due.