Question: Problem 2 Consider the network described in the table below. Immediate Optimistic Likely Pessimistic table [ [ Activity Predecessor ( s ) ,

Problem 2
Consider the network described in the table below.
Immediate Optimistic Likely Pessimistic
\table[[Activity Predecessor(s),\table[[Time],[(days)]],\table[[Time],[(days)]],],[W,none,4,6,14],[H,none,7,10,13],[C,W,3,5,7],[G,H,4,6,8],[E,H,3,3,3],[F,C,E,1,4,10]]
What is the probability of completing the project in 15 days or less?