Question: Problem 2 Consider the network described in the table below. Immediate Optimistic Likely Pessimistic Activity Predecessor ( s ) Time ( days ) Time (

Problem 2
Consider the network described in the table below.
Immediate Optimistic Likely Pessimistic
Activity Predecessor(s) Time (days) Time (days) Time (days)
W none 4614
H none 71013
C W 357
G H 468
E H 333
F C,E 1410
What is the probability of completing the project in 15 days or less?
Group of answer choices
about 22%
about 58%
about 72%
about 82%