Question: Problem 2 (drawn from problem 4 on page 162 of the text) A construction project is broken down into the following 10 activities: Activity Immediate

Problem 2 (drawn from problem 4 on page 162 of the text) A construction project is broken down into the following 10 activities: Activity Immediate Pred Weeks DD B,C vui wwwANAW D F G HI a. Please draw the network. b. What is the critical path? C. How many weeks will it take to complete the project? d. How much slack does each of the activities have