Question: Problem 2 E B 3 days 7 days A 2 days 4 days H H 6 days D 3 days F 3 days 2 days

Problem 2 E B 3 days 7 days A 2 days 4 days H H 6

Problem 2 E B 3 days 7 days A 2 days 4 days H H 6 days D 3 days F 3 days 2 days a. For the above network diagram, i. Identify the Critical path 2 point ii. Calculate the project duration. 1 point iii. An activity on the critical path is delayed by 10 days; calculate the impact on the project duration. 1 point iv. Calculate the `Slack Time of the activity X from the following data: Activity X Early start 15 Early finish 35 Late start 30 Late finish 50