Question: Explain all the steps and calculation in detail. 1. Draw the network diagram 2. List the network paths 3. Determine the critical path(s) 4. Determine

Explain all the steps and calculation in detail.

1. Draw the network diagram 2. List the network paths 3. Determine

1. Draw the network diagram 2. List the network paths 3. Determine the critical path(s) 4. Determine the float for each activity Duration Activity Dependency Float (Days) Start 0 A 8 Start B 5 E F 3 G 7 D 9 8 6 A B, H D, F C, I Start H 8 G 6 H J 5 K 2 J L 3 J Finish 0