Question: problem 2 - page 2 1 3 , textbook, 1 0 points total, have a sheet of paper and pencil to help yourself in solving
problem page textbook, points total, have a sheet of paper and pencil to
help yourself in solving the problem
Question points
A foot subdivision street is to be constructed:
The layout will be completed in three days;
The fill will be brought in over the course of eight days;
The compactiongrading will be completed in five days;
The asphalt topping will be done in three days; and
The striping will take one day to complete.
Using a minimum float guideline of one day, develop a linear schedule for this project. What is the project duration if
no activities are to be interrupted?
aNSWER THE FOLLVOWING
Question points
Saved
Layout activity work is starting on day and ending on day of the project.
Question options:
Compaction activity can start right after Layout is done
Yes, this is true if we assume constant production each day
Other activities cannot be deployed during these days timeframe
No it cannot be done in days
Question points
Asphalt topping is starting day and finishing day
Question options:
True
False
Question points
Striping activity starts on day and finish on day
Question options:
day & day start and finish
day & day start and finish
day & day start and finish
day & day start and finish
day & day start and finish
Question point
Activity crashing One certain way to make activity "Compaction" duration shorter is to:
Question options:
make Asphalt Topping activity duration longer
create a network diagram and see if this activity is noncritical
this is not possible
add more crews and equipment to it or split in multiple crews, if available
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock