Question: Problem 2 The following data were obtained from a project to build a pressure vessel. Activity Duration Predecessors A 6 weeks --- B 6 weeks

Problem 2

The following data were obtained from a project to build a pressure vessel.

Activity Duration Predecessors

A 6 weeks ---

B 6 weeks ---

C 5 weeks B

D 4 weeks A, C

E 5 weeks B

F 7 weeks D, E, G

G 4 weeks B

H 8 weeks F

I 5 weeks G

J 3 week I

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions. (12 points total)

  1. Calculate the scheduled completion time. (5 points)
  2. Identify the critical path. (3 points)
  3. What is the slack time (float) for activity A? (1 points)
  4. What is the slack time (float) for activity D? (1 points) e) What is the slack time (float) for activity E? (1 points) f) What is the slack time (float) for activity G? (1 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!