Question: The following data were obtained from a project to build a pressure vessel. Activity Duration Predecessors A......................6 weeks...........................--- B......................6 weeks...........................--- C......................5 weeks............................B D.......................4 weeks.......................A, C

The following data were obtained from a project to build a pressure vessel.
Activity Duration Predecessors
A......................6 weeks...........................---
B......................6 weeks...........................---
C......................5 weeks............................B
D.......................4 weeks.......................A, C
E.......................5 weeks............................B
F........................7 weeks..................D, E, G
G.......................4 weeks............................B
H.......................8 weeks............................F
I.........................5 weeks...........................G
J.........................3 weeks............................I
1. Construct a network diagram for the project.
2. Answer the following questions.
a) Calculate the scheduled completion time.
b) Identify the critical path.
c) What is the slack time (float) for activity A?
d) What is the slack time (float) for activity D?
e) What is the slack time (float) for activity E?
f) What is the slack time (float) for activity?

Step by Step Solution

3.41 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

1 Network diagram Basis the information given in question we will start w... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-A-S-S(1422).docx

120 KBs Word File

Students Have Also Explored These Related Cost Accounting Questions!