Question: The following data were obtained from a project to build a pressure vessel. Activity Duration Predecessors A......................6 weeks...........................--- B......................6 weeks...........................--- C......................5 weeks............................B D.......................4 weeks.......................A, C
Activity Duration Predecessors
A......................6 weeks...........................---
B......................6 weeks...........................---
C......................5 weeks............................B
D.......................4 weeks.......................A, C
E.......................5 weeks............................B
F........................7 weeks..................D, E, G
G.......................4 weeks............................B
H.......................8 weeks............................F
I.........................5 weeks...........................G
J.........................3 weeks............................I
1. Construct a network diagram for the project.
2. Answer the following questions.
a) Calculate the scheduled completion time.
b) Identify the critical path.
c) What is the slack time (float) for activity A?
d) What is the slack time (float) for activity D?
e) What is the slack time (float) for activity E?
f) What is the slack time (float) for activity?
Step by Step Solution
3.41 Rating (164 Votes )
There are 3 Steps involved in it
1 Network diagram Basis the information given in question we will start w... View full answer