Question: Problem 2 - The following table shows the tasks, durations, and predecessor relationships for an urban expressway repair. Draw the precedence network for the project
Problem The following table shows the tasks, durations, and predecessor relationships for an urban expressway repair. Draw the precedence network for the project and answer the questions that follow Please assume the Beta distribution for all activity times.
tableTasktableImmediatePredecessorsTime Estimates In WeeksOptimisticMost Lkely,PessimisticANone,BACADBEBGCHE F
a Draw the network diagram.
b Calculate the expected duration and variance of each activity.
c What are the ES earliest start and the LS latest start for each task based on the expected task times?
d What is the probability of completion of the project before week using the critical path based on the expected task times?
e What is the probability that the project will take more than weeks to complete?
f What is the probability that the project will be completed between the th and the th week?
g What is the project completion date that yields a chance of completion?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock