Question: Problem 2 Use this Activity-on-Arrow (AOA) diagram to determine the Early Start, Latest Start, Earliest Finish, Latest Finish, Slack, Critical Path and Project Duration. You

Problem 2

Use this Activity-on-Arrow (AOA) diagram to determine the Early Start, Latest Start, Earliest Finish, Latest Finish, Slack, Critical Path and Project Duration. You will only enter only certain answers online but you will need to calculate all to get the required answers

Problem 2 Use this Activity-on-Arrow (AOA)

Required answers for outline:

  • Earliest start time for Activity Node 10
  • Latest start time Activity Node 10
  • Earliest finish time Activity Node 10
  • Latest finish time Activity Node 10
  • Slack time Activity Node 10
  • Earliest start time Activity Node 11
  • Latest start time Activity Node 11
  • Earliest finish time Activity Node 11
  • Latest finish time Activity Node 11
  • Slack time Activity Node 11
  • Critical activities path (use - to separate the nodes)
  • expected duration of the project
2 10 5 8 12 10 3 11 6

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!