Question: Problem 2-11 (Algo) As operations manager, you are concerned about being able to meet sales requirements in the coming months. You have just been given
Problem 2-11 (Algo) As operations manager, you are concerned about being able to meet sales requirements in the coming months. You have just been given the following production report: JAN FEB MAR APR Units produced 2,255 1,755 2,755 2,955 Hours per machine 319 195 394 315 Number of machines 2 4 3 4 Find the average of the monthly productivity figures (units per machine hour). (Do not round intermediate calculations. Round your answer to 2 decimal places.)
A manufacturing shop is designed to operate most efficiently at an output of 1,150 units per day. In the past month, the plant averaged 920 units per day.
What was its capacity utilization rate last month? (Round your answer to 1 decimal place.)