Question: Problem 2-14 (Algo) As operations manager, you are concerned about being able to meet sales requirements in the coming months. You have just been given

Problem 2-14 (Algo)

As operations manager, you are concerned about being able to meet sales requirements in the coming months. You have just been given the following production report:

JAN FEB MAR APR
Units produced 2,125 1,625 2,625 2,825
Hours per machine 300 181 375 301
Number of machines 3 5 4 5

Find the average of the monthly productivity figures (units per machine hour). (Do not round intermediate calculations. Round your answer to 2 decimal places.)