Question: Problem 22-12 Seven jobs must be processed in two operations: A and B. All seven jobs must go through A and B in that sequence-A

Problem 22-12 Seven jobs must be processed in two

Problem 22-12 Seven jobs must be processed in two operations: A and B. All seven jobs must go through A and B in that sequence-A first, then B. Determine the optimal order in which the jobs should be sequenced through the process using these times: Position in Sequence Process A Process B Job Time Time 1 9 9 2 7 5 3 8 7 4 6 8 5 2 3 6 3 4 7 4 6