Question: Problem 3 . 1 7 table [ [ Time ] , [ Activity , a , m , b , Immediate predecessor / s

Problem 3.17
\table[[Time],[Activity,a,m,b,Immediate predecessor/s],[A,4,8,10,-],[B,2,8,24,A],[C,8,12,16,A],[D,4,6,10,A],[E,1,2,3,B],[F,6,8,20,E, C],[G,2,3,4,E, C],[H,2,2,2,F],[I,6,6,6,F],[J,4,6,12,D, G, H],[K,2,2,3,I, J],[Draw the network,,,,],[Find the CP,,,,]]
Find the slack activities and their individual values Determine the probability if the project is completed in less than equal to 50
 Problem 3.17 \table[[Time],[Activity,a,m,b,Immediate predecessor/s],[A,4,8,10,-],[B,2,8,24,A],[C,8,12,16,A],[D,4,6,10,A],[E,1,2,3,B],[F,6,8,20,E, C],[G,2,3,4,E, C],[H,2,2,2,F],[I,6,6,6,F],[J,4,6,12,D, G, H],[K,2,2,3,I, J],[Draw the network,,,,],[Find

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!