Question: Problem 3 A 1 0 0 kWdc PV system is being proposed for a commercial building in an area with 5 . 5 kWh /

Problem 3
A 100kWdc PV system is being proposed for a commercial building in an area with 5.5 kWh/m2/d insolation. The before taxcredit cost of the system is $5/Wdc. Assuming a 0.72 derate factor, a 30% renewables investment tax credit, $5/kWdc/year annual O&M, and a fixed charge rate of 15%/year:
a) What is the annual electricity production that might be expected? b) What is the levelized cost of energy?