Question: Problem 3 A fixed time isolated signal plan has L = 1 6 seconds ? ( ) Y ? c = 0 . 7 8

Problem 3
A fixed time isolated signal plan has L=16 seconds ?()Y?c=0.785. What ?()? is the optimum cycle tim and the minimum cycle time? What is the effective green time of phase i if yc,i=0.204? Roun your answers to the next integer value.
 Problem 3 A fixed time isolated signal plan has L=16 seconds

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!