Question: Problem 3 Consider the following project network. The numbers represent activity times in weeks. A, 2 B, 1 C, 1 E,3 H,5 J. 4 1,5

Problem 3 Consider the following project network.

Problem 3 Consider the following project network. The numbers represent activity times in weeks. A, 2 B, 1 C, 1 E,3 H,5 J. 4 1,5 Carry out a forward and backward path analysis and calculate ES, EF, LS, LF, and slack for each activity. Then please fill out the table below. Forward Pass Backward Pass Activity Slack LS-ES ES EF U LF-EF Slack A B C Time 2 1 1 3 5 5 E 1 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock