Question: Problem 3 Consider the following tasks that must be assigned to 4 workers on a conveyor - paced assembly line ( i . e .
Problem
Consider the following tasks that must be assigned to workers on a conveyorpaced assembly line ie a machinepaced line flow Each worker must perform at least task. There is unlimited demand.
tabletableTime to CompleteTask secondsTask Task Task Task Task Task Task Task Task Task Task Task
The current conveyorpaced assemblyline configuration assigns the workers in the following way:
Worker : Tasks
Worker : Tasks
Worker : Tasks
Worker : Tasks
a What is the capacity of the current line?
b What is the direct labor content?
c What is the average labor utilization do not consider any transient effects such as the line being emptied before breaks or shift changes
The firm is hiring a fifth worker. Assume that tasks are allocated to the workers to maximize capacity of the line, subject to the conditions that i a worker can only perform adjacent operations and ii all tasks need to be done in their numerical order.
d What is the capacity of this line now?
Again, assume the firm has hired a fifth worker. Assume further that tasks are allocated to maximize capacity of the line and that tasks can be performed in any order.
e What is the maximum capacity that can be achieved?
f What is the minimum number of workers that could produce at an hourly rate of units? Assume the tasks can be allocated to workers as described in the beginning ie tasks cannot be done in any order
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock