Question: Problem 3 . Eight jobs are to be processed through a single machine. The processing times and due dates are given here. Furthermore, assume that

Problem 3. Eight jobs are to be processed through a single machine. The processing times and due dates are given here. Furthermore, assume that the following precedence relationships must be satisfied:
[2->6->3; 1->4->7->8]
Determine the sequence in which these jobs should be done in order to minimize the maximum lateness subject to the precedence restrictions.