Question: Question 1) Eight jobs are to be processed through a single machine. The processing times and due dates are given here. Job Processing time Due

Question 1) Eight jobs are to be processed

Question 1) Eight jobs are to be processed through a single machine. The processing times and due dates are given here. Job Processing time Due date 1 2 A WN * com 7 2 00 NOR 10 Furthermore, assume that the following precedence relationships must be satisfied: Job Immediately preceeded by 6 4 a A WIN 1 5 6 2 4 8 Determine the sequence in which these jobs should be done in order to minimize the maximum lateness subject to the precedence restrictions