Question: Problem 3 : Three step process Consider a worker - paced line with three steps, each of which is staffed with one worker. The processing

Problem 3: Three step process
Consider a worker-paced line with three steps, each of which is staffed with one worker. The processing times are 3
minutes per item for step 1,4 minutes per item in step 2 and 5 minutes per item in step 3.
If the process is operated as a push system, what will happen to inventory?
Inventory will not pile up either before step 2, neither will it pile up before step 3.
Inventory will pile up both before step 2 and before step 3.
Inventory will pile up before step 3 but not before step 2.
Inventory will pile up before step 2 but not before step 3.
If the process is operated as a push system, what is true about the utilization of the workers in
steps 1,2 and 3?
Utilization of worker 1 Utilization of worker 2 Utilization of worker 3
Utilization of worker 1= Utilization of worker 2= Utilization of worker 3
Utilization of worker 1> Utilization of worker 2> Utilization of worker 3
If the process is operated as a pull system, at what rate does the process produce?
At the rate marked by the capacity of worker 3
At the rate marked by the capacity of worker 2
At the rate marked by the capacity of worker 1
If the process is operated as a pull system, what is true about the utilization of the workers in
steps 1,2 and 3?
Utilization of worker 1 Utilization of worker 2 Utilization of worker 3
Utilization of worker 1> Utilization of worker 2> Utilization of worker 3
Utilization of worker 1= Utilization of worker 2= Utilization of worker 3
3 extra credit
points
 Problem 3: Three step process Consider a worker-paced line with three

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!