Question: Problem 3.7b Question Help In the following table the activities with their precedence sequence and expected time (weeks) are listed for Lillian Fok's construction project

Problem 3.7b Question Help In the following table
Problem 3.7b Question Help In the following table the activities with their precedence sequence and expected time (weeks) are listed for Lillian Fok's construction project and on the right the precedence network is shown: Activity J K L M N Nodes 1-2 1-3 2-4 2-3 3-4 4-5 3-5 Time (weeks) 8 8 6 3 4 7 6 P The project length is weeks. Enter your answer in the answer box and then click Check Answer Cloar All Check Answer 1 pan remaining