Question: Problem 3.7b Question Help In the following table the activities with their precedence sequence and expected time (weeks) are listed for Lillian Fok's construction project

Problem 3.7b Question Help In the following table

Problem 3.7b Question Help In the following table the activities with their precedence sequence and expected time (weeks) are listed for Lillian Fok's construction project and on the right the precedence network is shown: Activity j K L M N O P Nodes 1-2 1-3 2-4 2-3 3-4 4-5 3-5 Time (weeks) 10 8 6 3 2 7 7 The project length is 45 weeks