Question: Problem 4 . 0 ( 2 5 Points ) A new product made from recycled bio - plastics needs 2 0 labor hours to complete

Problem 4.0(25 Points) A new product made from recycled bio-plastics needs 20 labor hours to complete the build for the first unit. If production operates at a 85% learning curve rate, calculate the average labor hours required per unit to produce three units.