Question: Problem 4 - 1 5 For the network shown: a - 1 . Determine the critical path. A - B - D - G A
Problem
For the network shown:
a Determine the critical path.
ABDG
ACFG
ACEG
ABEG
a Determine the early completion time in weeks for the project.
Early completion time
weeks
For the data shown, reduce the project completion time by three weeks. Assume a linear
cost per week shortened.
b Which activities in order of reduction would be shortened?
BBB
GEA
BGD
DBC
b Find the resulting cost to crash.