Question: The Question 2 information for a project is given in the Table below (time in weeks): Activity Immediate predecessors Activity time (t) A - 2

The Question 2

information for a project is given in the Table below (time in weeks):

Activity

Immediate predecessors

Activity time (t)

A

-

2

B

A

6

C

A

4

D

C

5

E

B

2

F

E, D

8

G

F

5

H

A

4

I

H

10

J

I

3

K

G, J

2

  1. Draw a network for this project
  2. Determine the critical path
  3. Determine the earliest and latest activity times
  4. Determine slack time for each activity