Question: The Question 2 information for a project is given in the Table below (time in weeks): Activity Immediate predecessors Activity time (t) A - 2
The Question 2
information for a project is given in the Table below (time in weeks):
| Activity | Immediate predecessors | Activity time (t) |
| A | - | 2 |
| B | A | 6 |
| C | A | 4 |
| D | C | 5 |
| E | B | 2 |
| F | E, D | 8 |
| G | F | 5 |
| H | A | 4 |
| I | H | 10 |
| J | I | 3 |
| K | G, J | 2 |
- Draw a network for this project
- Determine the critical path
- Determine the earliest and latest activity times
- Determine slack time for each activity