Question: Problem 4 - 2 3 ( Static ) What type of chart compares the current project schedule with the original baseline schedule so that deviations
Problem Static
What type of chart compares the current project schedule with the original baseline schedule so that deviations from the original plan can be easily noticed?
Multiple Choice
Project calendar
Project task tree
Milestone chart
Bar chart