Question: What type of chart compares the current project schedule with the original baseline schedule so that deviations from the original plan can be easily noticed?
Step by Step Solution
3.43 Rating (153 Votes )
There are 3 Steps involved in it
Tracking Gantt chart compares the current project schedule w... View full answer